14 Home Page. The Weld Industry 15
  All Weld &
Steels Programs
 
  MIG Weld
Steels
  > 4mm
 
  MIG Weld
Steels < 4mm
 
Pulsed MIG  
  MIG Weld Gases  
  MIG Weld Advice on Equipment  
  Robots & Weld Management  
  Robots and MIG
Welding Tips
 
  MIG / Flux Cored
Pipe Welds
 
  Advice and QA Welding Forum  
  Ed's Training Materials  
Ed's Projects  
12 Ed's Bio Contact  
.





PULSED MIG CLAD AND OVERLAY WELDS:



Above: This sad, manual clad weld photo was taken in 2008 and prodly dispalyed on the cover of a welding magazine. The Inconel clad welds were made using the latest 2008 pused MIG equipment from Miller. This poor excuse for a weld operation is not the way to clad weld boiler tubes with Inconel or Stainless MIG weld wires. Pooe weld settings for Inconel, excess weld heat for the water walls. No weld dilution or fusion controls. Poor weld overlap. Excess weld start / stops and a 1000 other weld / boiler issues that will result.



E
d's weld process control approach to water wall cladd welds,
using 2005 pulsed MIG equipment

MIG CLAD APPLICATION.
BOILER WATER WALLS



Ed's contribution to the power and
waste management industry


2007: Welding Services (WSI) Atlanta: WSI is primarily involved in repairs and refurbishment in the power, waste energy and nuclear industries. In terms of water wall cladding, WSI has clad approx. 80% of the North American boilers. Each year WSI uses approx. one million pounds of Inconel 625-622 and 300 series stainless MIG wires for cladding boiler water wall tubes.

CREATED A NEW PATENT:
While WSI has produced some of the most innovative, automatic MIG cladding equipment available in North America, WSI did not have a resident MIG process control expert who had the expertise necessary to make radical improvements to it's water wall clad MIG welds. Ed was contracted for this work by the WSI engineering manager. In less than 6 months, as the following pictures indicate, Ed dramatically improved the water wall overlay weld quality and a new clad weld patent was developed for this industry



IMPROVED BOILER LIFE AND OPERATING EFFICIENCY: As many in the power industry are aware, with any cladding application "less is always better". The boilers operate more efficiently when the clad surface is thinner and the clad weld pass thickness is uniform and free of weld defects. Ed's new patent dramatically improved the clad weld quality and dramatically reduced the typical single pass clad weld thickness:


REDUCED CONSUMABLE WELD COSTS. With Inconel clad wires at approx. $22 per-pound and large areas to be clad, weld consumables are typically a large part of the cost of a boiler clad application. Ed's new procedure reduced the amount of clad weld overlay typically required by approx. 28%.

SINGLE PASS / DILUTION: With water wall clad applications, the minimum, "single pass" Inconel weld clad chemistry required is 20% chrome. To attain the minimum chrome requirements the pulsed MIG weld procedures had to ensure the weld dilution was less than 8%. The vertical down clad welds had to attain minimum weld dilution with consistent weld fusion on the carbon steel boiler tubes.

COST EFFECTIVE WITH HIGH DEPOSITION RATES:
Of course when cladding large areas sometimes 1000 to 10.000 sq. feet, the clad weld process improvements must also from a weld deposition rate perspective be cost affective. Ed's new patented procedure and the WSI unique, automated weld equipment enabled a single operator controlling two guns to deposit 26 - 28 lbs/hr.





With Clad welds on boilers, less is always better,
unless you sell the weld consumables.


 


This picture was considered an
optimum, Inconel, Vertical Down, Pulsed Clad MIG weld.



After pulsed MIG weld process improvements.
The final 622, single pass, clad weld results were developed by Ed in 2006.


Ed's MIG clad welds, note the smooth surface and improved weld ties ins.
This application from a $6000 pulsed MIG power source now
has has a smooth finish similar to a $250.000 laser / powder overlay.


On left, traditional clad method for vert down 622 overlay (as welded not cleaned).
On right Ed's process improvements, again both as welded.


 

 





Note: All photos are untouched and no weld cleaning except brushing was provided.


 

 


Weld process expertise will always ensure that any
weld process utilized runs without weld spatter.


2006: Ed's weld on the left typical welds on the right:

 


The vertical down 622 Inconel / stainless clad MIG welds were derived from a low cost, six thousand dollar power source and a MIG gas mix developed by Ed. (See gas data section). The welds also required an engineering manager that believed that there was more to MIG welding than asking the advice of a Lincoln sales rep or an operator throwing a switch that initiates the arc. It also helped that WSI had excellent, unique automated weld equipment that compensated for the water wall curves (wire stick out variations). Ed's clad development was complete in 2006. WSI applied for the Patent during 2006 - 2007.



 


 

 

Cladding and Hydro-Processing Vessels

 

 

2006: Another common Global Application
overlay application influenced by Ed:




The Electro Slag Strip Electrode Process
applying ER 347 clad welds.

 


The Electro Slag Common Application. In the refinery industry, pressure vessels used in high temperature, high pressure "hydrogen service" such as hydrocracking and hydrotreating are usually constructed of Chrome / Molly or Vanadium modified Chrome / Moly steels. To overcome corrosion areas with these vessels, clad welds of ER 347 alloy are typically applied to plate or to wasted areas on pressure vessels.

The most common, global cladding "process" utilized for plate cladding used for hydrogen service, has been the Electro Slag Welding (ESW). This process uses strip electrodes two to three inches wide. On some applications a butter layer of ER 309 is requested followed by a surface layer of ER 347 for the clad surface. On other applications a single layer of ER 347 is applied.

With the ESW process, high deposition welds result from weld current > 600 amps. The ESW process has been considered unique in that the large size of the strip electrode results in low weld current density resulting in "low weld dilution". The down side of this process is;

[a] its a "single" electrode process,

[b] It's large, cumbersome and weld position restricted,

[c] the cost of the clad consumables and flux are high,

[d] there are few companies with expertise. Many North American vessels are clad in Japan.


Utilizing a unique MIG weld wire found by Ed, and cladding equipment developed by WSI, has enabled the ability to produce "single pass", MIG layer clad 347 welds that meet the hydrogen service 347 clad thickness, chemistry and ferrite requirements. In comparison to the ESW and SAW process, thanks to the large differences in consumable costs and the multi MIG gun capability, it's now possible to produce the 347 MIG clad welds, depending on the application with a 30 to 50% cost reduction.







In contrast to the more costly ESW and SAW processes, the MIG clad procedure developed by Ed and WSI enables cladding on a much wider range of applications, and allows the flexibility to provide the vessel cladding at any site locations. This dramatically reduces the vessel lead times or shipping costs to have this work done.




ED'S MIG PROCESS EXPERTISE CHANGED
THIS TRADITIONAL GLOBAL 347 ELECTRO SLAG
AND SAW WELD APPLICATION.

To a clad MIG process that's faster, provides less distortion,
has less heat effect on the steel, costs less and is more versatile.

 


MIG Cladding in the 1980's

In the 1980s, before the development of pulsed MIG, Ed produced this Inconel 622 MIG clad weld on a boiler tube. On the right is the clad weld fusion profiles that the power industry was accustomed to.

 

Ed's Inconel clad weld on the left was made without any cooling medium and made with a MIG process developed in 1963.


 

1983

This clad weld surprised the metallurgist who examined it,
as their was no evidence of the 622 weld dilution with the base alloy,
or evidence of a weld's heat affected zone.

 

 


The Clad Weld Challenges
of the next decade.


When you have a clad welding challenges on those ID-OD power plant, refinery, and well head equipment such as ID welds on adapter flanges,bonnets, studded tees, tree caps, weld neck flanges, gate valves, please note, you can invest hundreds of thousands of dollars in sophisticated overlay equipment and never quite get that application the way it could be. You could ask a salesman for your pulsed clad MIG advice, or you could learn how to control this important process and produce clad welds without weld rework.






Return to home page

 



 


Email Ed Craig at ecraig@weldreality.com   -  Phone Eastern Time. USA. 828 658 3574